| CIVIL WORK FOR LATI UPGRADE 3 PROJECT, BERAU, EAST KALIMANTAN |
|
| P.T. BERAU COAL , February 2008 - October 2008 |
|
| - Civil Work Construction : |
|
- Chain Feeder, Crusher, Retaining Wall Crusher Conveyor.
- Stacking Conveyor Foundation, Reclaim Tunnel Hopper, Extension Barge Loading and Steel Coloumn for Stacking Conveyor.
|
|
| |
|
| COAL WASH PLANT CONSTRUCTION PROJECT, BONTANG, EAST KALIMANTAN |
|
| P.T. INDOMINCO MANDIRI , October 2004 – March 2005 |
|
| - Wash Plant Construction : |
|
- Foundation of Retaining Wall : 305 m3, Steel Structure Building : 30.575 kg, Machines erection : 70.000 kg, Office, Electrical room, Store : 135 m2.
- Stacker and Conveyor system : 200 ton/hr, Electrical, PLC control system, Water supply and Piping system : 500 m3/hr.
- Miscellaneous work, Water Treatment Sump and Tailing Discharge Pipe (HDPE) : 1.260 m.
|
|
| |
|
COAL LOADING JETTY AND CONVEYOR FOUNDATION CONSTRUCTION PROJECT
SAMARINDA, EAST KALIMANTAN |
|
| P.T. MAHAKAM SUMBER JAYA , 2004 |
|
| - Loading Jetty Works, - 6 units of Breasting Dolphin for 8.000 DWT Barge |
|
- Steel Pipe Pile Foundation: Ø 609 mm, t = 12 mm, L = 33, Concrete Pile Cap and Fender Wall Structure.
- 12 units Rubber Fender for Breasting Dolphin type DA-A.400 H - 2000 L.
|
|
| - 3 units Conveyor Tower Support |
|
- Steel pipe pile foundation Ø 609 mm, t = 12 mm, L = 30 m, Concrete Pile Cap.
|
|
| - 7 Units Steel Walk Way |
|
- Steel Pipe Pile Ø 609, t = 9 mm for Main Structure.
|
|
| |
|
| RENOVATION DOLPHIN PROJECT NEW COAL LOADING JETTY, EAST KALIMANTAN |
|
| P.T. JORONG BARUTAMA GRESTON , 2003 |
|
| - Loading Jetty Works: - 6 units of Breasting Dolphin for 8.000 DWT Barge |
|
- Steel Pipe Pile Foundation,Ø 609, t = 12 mm, L = 24 m, Concrete Pipe Cap and Fender Wall Structure.
- 12 units Rubber Fender for Breasting Dolphin Type DA-A.400 H - 1500 L, 6 units Bollard 35 ton.
|
|
| - Conveyor Foundation Works: |
|
- 2 units Conveyor Tower Support.
- Steel Pipe Pile Foundation, Ø 609, t = 12 mm, L = 24 m,\.
- Concrete Pile Cap, Demolish 6 units Marine Steel Gravity Dolphin Ø 6 m, H = 8 m.
- Repair 1 unit Marine Steel Gravity Dolphin Ø 8 m, H = 8.5 m.
|
|
| |
|
| COAL LOADING JETTY PROJECT, SAMBARATA, TANJUNG. REDEB, BERAU, EAST KALIMANTAN |
|
| P.T. SUMBER MITRA JAYA , 2000 |
|
| - Loading Jetty: - 6 units of Breasting Dolphin for 5.000 DWT Barge |
|
- Steel Pipe Pile Foundation: Ø 609 mm, t = 12 mm, L = 48 mStructure.
- Concrete Pile Cap and Fender Wall, 12 units Rubber Fender for Breasting Dolphin type DA-A.400 H - 1,500 L.
- 6 units Bollard 35 ton.
|
|
| - 2 units Conveyor Tower Support |
|
- Steel Pipe Pile Foundation Ø 609 mm, t = 12 mm, L = 36 m.
- Concrete Pile Cap - 6 units Steel Walk Way.
- Steel Pipe, Ø 609, t = 9 mm for Main Structure and Steel Pipe, Ø 609, t = 9 mm for Main Structure.
|
|
| |
|
| JORONG COAL PORT PROJECT, JORONG COAL PORT PROJECT |
|
| P.T. JORONG BARUTAMA GRESTON , 1998 |
|
| - Construction of Rock Armoured Slope Protection |
|
| - Construction of Breakwater |
|
| - Construction of Dolphins : Gravity Steel Tank Dolphins : |
|
- 1 unit Ø 8 m, H = 8.5 m, 6 units Ø 6 m, H = 8.5 m, 5 units Walk way W = 1 m'.
|
|
| - 1 unit Walk Way, W = 2 m, - Loading Conveyor Foundation |
|
| - Reclaim Conveyor Foundation, |
|
| - Concrete Tunnel Foundation, - Concrete Feeder Conveyor Foundation |
|
| - Tripper Conveyor Foundation, |
|
| - Transfer Conveyor Foundation, - Screen Foundation |
|
| - Crusher Foundation, - Concrete Retaining Wall |
|
| |
|
| JETTY AND DOLPHINS PROJECT, SUARAN PORT AND LATI PORT, TANJUNG REDEB, BERAU, EAST KALIMANTAN |
|
| P.T. BERAU COAL , 1997 |
|
| - Coal Loading Jetty for 10,000 D.W.T Barge, * 9 units Breasting Dolphin |
|
- Steel Pipe Pile Foundation, Ø 1,000 mm, t = 14 mm, L = 36 m, Concrete Pile Cap and Fender Wall Structure, Rubber Fender Type H = 500, L = 2000, Bollard Capacity: 50 ton.
- Marine Ladder, Marine Navigation Lighting, Walk Way and Walk Way Support, Repair Dolphin at Sungai Lati Port, Steel Pipe Dolphine Structure Ø 1,000 mm, t = 14 mm, L = 12 m, Rubber Fender.
|
|
| |
|