| RETAINING WALL WORK PROJECT, JALAN BUJANGGA, TANJUNG REDEB, BERAU, EAST KALIMANTAN |
|
| DINAS PEKERJAAN UMUM , February 2008 - November 2008 |
|
| - Retaining Wall Work: |
|
- Steel Sheet Pile, ( FSP IIIA x 81 m'.), Steel Sheet Pile, (FSP IVA x 45 m'.)
|
|
| |
|
| RETAINING WALL WORK PROJECT, P. TENDEAN-MARTADINATA, BALIKPAPAN, EAST KALIMANTAN |
|
| DINAS PEKERJAAN UMUM , 2007 |
|
| - Retaining Wall Work: |
|
- Steel Sheet Pile FSP, 1.800 m' (0,4 @ 12.00 m).
|
|
| |
|
| RETAINING WALL WORK PROJECT PULAU DERAWAN , TANJUNG REDEB, BERAU, EAT KALIMANTAN |
|
| DINAS PEKERJAAN UMUM , June 2006 - December 2006 |
|
| - Retaining Wall Work: |
|
- Driving Concrete Sheet Pile and Common Embankment.
|
|
| |
|
| RETAINING WALL WORK PROJECT SEI KANDILO - JLN YOS SUDARSO SAMARINDA, EAST KALIMANTAN |
|
| DINAS PEKERJAAN UMUM , 2002 |
|
| - Retaining Wall Work : |
|
- Bore Pile, Driving Concrete Sheet Pile, Common Embankment.
|
|
| |
|
| RETAINING WALL WORK PROJECT SANGALAKI - JLN P. DERAWAN BERAU, EAST KALIMANTAN |
|
| DINAS PEKERJAAN UMUM , 2001 |
|
| - Retaining Wall Work: |
|
- Steel Sheet Pile FSP III A x 15 m, Soil Filling.
|
|
| |
|
| RETAINING WALL SEI KANDILO JALAN YOS SUDARSO PROJECT BALIKPAPAN, EAST KALIMANTAN |
|
| DINAS PEKERJAAN UMUM , 2001 |
|
| - Retaining Wall Work: |
|
- Driving Concrete Sheet Pile and Common Embankment.
- Prestressed Concrete Spun Pile 94 pcs of Ø 600 mm: 11 m, JIS A 5335-1985.
|
|
| |
|
| PILE SLAB PROJECT JALAN INHUTANI, BERAU, EAST KALIMANTAN |
|
| DINAS PEKERJAAN UMUM , 2001 |
|
| - Gravity Retaining Wall |
|
- Pile Slab, length 40 m, Steel Pipe Pile Ø 400 mm -18 m, 27 pcs.
|
|
| - Reinforced Concrete Beam and Slab. |
|
| - Asphalt Road Works |
|
| |
|
| RECLAMATION PROJECT, PASAR BARU, BALIKPAPAN, EAST KALIMANTAN |
|
| DINAS PEKERJAAN UMUM , 2001 |
|
| - Reclamation Work, Phase III: |
|
- Concrete Sheet Pile for Retaining Wall, Back Fill with Sand and selected material and Armour Stone 500 kg/pcs for counter weight.
|
|
| |
|
| RETAINING WALL WORK PROJECT JALAN A. YANI, TANJUNG REDEB, BERAU, EAST KALIMANTAN |
|
| DINAS PEKERJAAN UMUM , 2000 - 2001 |
|
| - Retaining Wall Work: |
|
- Steel Sheet Pile, ( FSP IIIA x 15 m, FSP IVA x 15 m, FSP IVA x 20 m.)
- Anchor Steel Pipe Pile, Ø 500 and Ø 600 mm and Soil Filling 40,000 m3.
|
|
| |
|
| CONCRETE SHEET PILE WORK, JALAN PASAR BARU, BALIKPAPAN, EAST KALIMANTAN |
|
| DINAS PEKERJAAN UMUM , 2000 |
|
| - Retaining Wall Work: |
|
- Concrete Sheet Pile, ( W 350 B ).
|
|
| |
|
| |
|