MECHANICAL, ELECTRICAL AND INSTRUMENTATION WORK
 
   
 
.............................................................................................................................................................................................................................
 
 
Plant Facilities
 
     
     
 
TUNU FIELD DEVELOPMENT PROJECT - PHASE 12, CONTRACT TP 12 / EPSC 1. TUNU, EAST KALIMANTAN  
TOTAL E&P INDONESIE , December 2007 - June 2009  
Engineering, Procurement, Supply, Construction, Installation and Pre-Commissioning of the New GTS's Bx, Fx, Nx and Tie-Ins to Existing Facilities.  
- The PLANT comprises  
  • Three (3) new GTS's (Bx, Fx, and Nx) with their associated Equipment and Materials Tie-Ins works of
    the GTS to existing adjacent trunklines
  • New extension and integration of telecommunication and control system to TUNU Field telemetry and Control system at TMP2, CPU and NPU related to GTS Bx, Fx and Nx
 
   
SETURIAN DECK FIT OUT PROJECT, SETURIAN, EAST KALIMANTAN  
CHEVRON INDONESIA Company , July 2007 - April 2008  
- Engineering  
  • Re-Hazop study sand Installation of 64 Well Pumps
  • Interface engineering with ICS, Pre. and Decommisioning assistance
 
- Structural  
  • Supply, Fabrication and install : Structural wings, Electrical / Instrumentation Room
 
- Mechanical/Package  
  • Supply and Install: Slop pump, Instrument Gas Package, CO2 Snuffing package, Methanol Injection Package,Corrosion Inhibitor Package, 22 kips pedestal Crane, 80 KW Generator-Set, Wellhead Control Panel for 8 wells
  • Install of Test: Separator, Slop Tank, Pig Launcher 9V-1200
 
- Piping  
  • Supply, Fabrication and Install for All piping system, such as production header, Test header, Flow line, Manifold, Vent system, Instrument air system, etc.(for 4 wells)
 
- Electrical / Instrumentation.  
  • Supply and install all field instrument, such as SDV, PSV, TT, PT, FE, etc.(for 4 wells) Supply and install for all tubing, cable included Tray
 
- Structural Steel weight: Pile 132 M-ton, Jacket 75 M-ton, Platform 175 M-ton  
- Water depth : 9 meter  
   
THE EPSC, TRANSPORTATION, HOOK UP & ASSISTANCE DURING COMMISSIONING OF THE NEW WELLHEAD PLATFORM AT GTS Kx AND Lx (TP 10 / EPSC 2).  
TOTAL E&P INDONESIE , April 2007 - April 2008  
Engineering, Procurement, Supply, Pre-fabrication, Construction, Installation, Testing and Pre-Commissioning of the GTS's and all Components, Equipment and Materials thereto and Assistance to Company during commissioning and start-Up of the Plant.  
- The PLANT comprises  
  • Two (2) Adjacent Wellhead Platforms,
  • Two (2) Bridge Platforms
  • Two (2) Walkways,One of each to GTS Kx and Lx installed as part of the scope of TP 10 / EPSC 2
  • Tie-Ins Works of the New Wellhead Platforms to the Existing GTS
  • New Extension and Integration of Telecommunication and Control System to TUNU Field Telemetry and Control
 
System at Central Processing Unit (CPU) and TUNU North Processing Unit (NPU)-NCR Building  
Well Conductors Pipes (Piled up to 110 meter depth) for the Wellhead Platforms  
   
THE HANDIL BURN PIT DECOMMISSIONING PACK 2, STEP 1 HANDIL, EAST KALIMANTAN  
TOTAL E&P INDONESIE , July 2006 - January 2007  
Decommissioning Burn Pit and Construction of Catch Pit  
Setting out and topographical survey, - Site clearing, - Excavation and backfilling, - Treatment polluted soil
 
- Supply, Spread and Compact clean Soil / Sand, mix fertilizer NPK161616,dismantling
 
- Unused steel parts, Supply, Spread and Compact soil cement  
- Supply and Install reinforced concrete, - Supply and Install enviromat bentonite clay liner 100  
- Supply and Install GSE HDS high density polyethylene Geomembrane textured 2 mm thickness  
   
TUNU FIELD DEVELOPMENT PROJECT - PHASE 10 CONTRACT TP 10 / EPSC 1. TUNU, EAST KALIMANTAN  
TOTAL E&P INDONESIE , March 2005 - January 2007  
Engineering, Procurement, Supply, Pre-fabrication, Construction, Installation, Testing and Pre-Commissioning of the GTS's and all Components, Equipment and Materials thereto and Assistance to Company during commissioning and start-Up of the Plant.  
- The PLANT comprises  
  • Four (4) new GTS's (Ax, Kx, Lx, Ix) with their associated Cold Vents as Extensions of Existing GTS
  • Eleven (11) Associated Adjacent Wellhead Platforms
  • Four (4) Reception Remote Wellhead Platforms, * Four (4) ESDV Platforms
  • Associated Flowlines, Walkways and Offsites for Four (4) GTS's
  • Tie-Ins Works of the New GTS's to the Existing Adjacent trunklines including new ESDV & Tripod
  • New Extension and Integration of Telecommunication and Control System to TUNU Field Telemetry and Control System at Central Processing Unit (CPU) and TUNU North Processing Unit (NPU) - NCR Building
  • Well Conductors Pipes ( 110 m' depth) for all Adjacent and Reception Remote Wellhead Platforms
 
   
ENGINEERING, PROCUREMENT, FABRICATION, INSTALLATION SERVICES CO2 REMOVAL PLANT PROJECT, LAWE-LAWE, EAST KALIMANTAN  
UNOCAL INDONESIA Company , July 2001 - January 2002  
- Engineering, Procurement, Fabrication and Installation.  
  • Soil Investigation and Detail Design, - Transportation and Installation of Heavy Lift, - Civil Works
  • Piping and Insulation Works, - Electrical and Instrument Works, - Equipment Installation
 
   
INSTALLATION OF LP GAS TRUNKLINE FROM SATELLITE # 6 TO # 5 NILAM FACILITY DEBOTTLENECKING PROJECT, NILAM, EAST KALIMANTAN  
VICO INDONESIA , April 2001 - August 2001  
- Installation of: 2 lines Trunkline Ø 10" River Crossing and 4 nos Scrapper Launcher / Receiver  
- Installation of: Electrical, Instrument and Civil Foundation  
   
TO PERFORM PROCUREMENT OF MATERIAL AND CONSTRUCTION / PIPING INSTALLATION FOR SLUG CATCHER ( M - 205 ) PROJECT, GRESIK, EAST JAVA  
KODECO ENERGY Company Ltd , 2000  
- Supply of Pipes, Valves and Fittings, - Supply Manway and Structural Platform  
- Construction Works: Tie-ins to the Existing, Slug Catcher  
   
ENGINEERING, SUPPLY AND INSTALLATION OF BADAK BUILDING AREA FIRE AND GAS PROTECTION SYSTEM (PHASE II), EAST KALIMANTAN  
VICO INDONESIA , 1999  
- Engineering, - Supply, Fabrication and Installation of:FGPS Panel,  
- Supply and Installation of Detectors, Field Wiring and Accessories,  
- Existing Fire and Gas Protection System Removal  
- Inspection, Testing and Commissioning  
   
PTA POLYPRIMA PROJEC, ANYER, WEST JAVA  
P.T. POLYPRIMA KARYA REKSA , 1997  
- Piping Works: Vol. 240,000 Dia-in. Stainless Steel, Carbon Steel, Titanium, Hastelloy, PVC and FRP  
- Erection of Steel Structure, weight 5,500 ton  
- Equipment Installation, weight 5,800 ton, The heaviest 240 ton highest 68 m  
- Assembly and installation of: 650 ton Stainless Steel: * Batch Tank: 2 units, * Silos: 2 units  
- C.S. Fuel Storage Tank: 1 unit  
   
GRESIK COPPER SMELTER PROJECT, GRESIK, EAST JAVA  
CHIYODA INTERNATRIONAL INDONESIA (Main Contractor) , 1997 - 1998  
- Piping Works: (PVC/FRP, CS, SS304 and 316, CS, Low Temperature, Galvanized)  
  • Fabrication and Installation of Piping works for Process,Total work volume: 235,000 Dia -in.
 
   
DOW POLYMERS INDONESIA PROJECT, MERAK, WEST JAVA  
P.T. DOW POLYMERS INDONESIA , 1994  
- Equipment Installation and Alignment, 180 units  
- Piping Fabrication and Installation of: * Carbon Steel 30,852 Dia -in., * Pipe Support 20 ton  
- Installation of Prefabricated Steel Structure, Total weight: 594 ton  
   
94 PREMIX BLENDING PLANT PROJECT, KALIBARU, TANJUNG PRIOK, JAKARTA  
P.T. HUMPUSS , 1993 - 1994  
- Engineering, Procurement, Fabrication, Erection  
- Testing, Inspection and Coating of Storage Tank:  
  • 6,000 m3 ( Ø 24.38 x 12.8) m : 3 units, * 2,330 m3 ( Ø 15.24 x 12.8) m : 2 units
 
- Piping Work: 20,000 Dia-in. - Pumps Installation