| TUNU FIELD DEVELOPMENT PROJECT - PHASE 12, CONTRACT TP 12 / EPSC 1. TUNU, EAST KALIMANTAN |
|
| TOTAL E&P INDONESIE , December 2007 - June 2009 |
|
| Engineering, Procurement, Supply, Construction, Installation and Pre-Commissioning of the New GTS's Bx, Fx, Nx and Tie-Ins to Existing Facilities. |
|
| -
The PLANT comprises |
|
- Three (3) new GTS's (Bx, Fx, and Nx) with their associated Equipment and Materials Tie-Ins works of
the GTS to existing adjacent trunklines
- New extension and integration of telecommunication and control system to TUNU Field telemetry and Control system at TMP2, CPU and NPU related to GTS Bx, Fx and Nx
|
|
| |
|
| SETURIAN DECK FIT OUT PROJECT, SETURIAN, EAST KALIMANTAN |
|
| CHEVRON INDONESIA Company , July 2007 - April 2008 |
|
| -
Engineering |
|
- Re-Hazop study sand Installation of 64 Well Pumps
- Interface engineering with ICS, Pre. and Decommisioning assistance
|
|
| - Structural |
|
- Supply, Fabrication and install : Structural wings, Electrical / Instrumentation Room
|
|
| -
Mechanical/Package |
|
- Supply and Install: Slop pump, Instrument Gas Package, CO2 Snuffing package, Methanol Injection Package,Corrosion Inhibitor Package, 22 kips pedestal Crane, 80 KW Generator-Set, Wellhead Control Panel for 8 wells
- Install of Test: Separator, Slop Tank, Pig Launcher 9V-1200
|
|
| - Piping |
|
- Supply, Fabrication and Install for All piping system, such as production header, Test header, Flow line, Manifold, Vent system, Instrument air system, etc.(for 4 wells)
|
|
| -
Electrical / Instrumentation. |
|
- Supply and install all field instrument, such as SDV, PSV, TT, PT, FE, etc.(for 4 wells) Supply and install for all tubing, cable included Tray
|
|
| -
Structural Steel weight: Pile 132 M-ton, Jacket 75 M-ton, Platform 175 M-ton |
|
| -
Water depth : 9 meter |
|
| |
|
| THE EPSC, TRANSPORTATION, HOOK UP & ASSISTANCE DURING COMMISSIONING OF THE NEW WELLHEAD PLATFORM AT GTS Kx AND Lx (TP 10 / EPSC 2). |
|
| TOTAL E&P INDONESIE , April 2007 - April 2008 |
|
| Engineering, Procurement, Supply, Pre-fabrication, Construction, Installation, Testing and Pre-Commissioning of the GTS's and all Components, Equipment and Materials thereto and Assistance to Company during commissioning and start-Up of the Plant. |
|
| -
The PLANT comprises |
|
- Two (2) Adjacent Wellhead Platforms,
- Two (2) Bridge Platforms
- Two (2) Walkways,One of each to GTS Kx and Lx installed as part of the scope of TP 10 / EPSC 2
- Tie-Ins Works of the New Wellhead Platforms to the Existing GTS
- New Extension and Integration of Telecommunication and Control System to TUNU Field Telemetry and Control
|
|
| System at Central Processing Unit (CPU) and TUNU North Processing Unit (NPU)-NCR Building |
|
| Well Conductors Pipes (Piled up to 110 meter depth) for the Wellhead Platforms |
|
| |
|
| THE HANDIL BURN PIT DECOMMISSIONING PACK 2, STEP 1 HANDIL, EAST KALIMANTAN |
|
| TOTAL E&P INDONESIE , July 2006 - January 2007 |
|
| Decommissioning Burn Pit and Construction of Catch Pit |
|
Setting out and topographical survey, - Site clearing, - Excavation and backfilling, - Treatment polluted soil |
|
- Supply, Spread and Compact clean Soil / Sand, mix fertilizer NPK161616,dismantling
|
|
| - Unused steel parts, Supply, Spread and Compact soil cement |
|
| - Supply and Install reinforced concrete, - Supply and Install enviromat bentonite clay liner 100 |
|
| - Supply and Install GSE HDS high density polyethylene Geomembrane textured 2 mm thickness |
|
| |
|
| TUNU FIELD DEVELOPMENT PROJECT - PHASE 10 CONTRACT TP 10 / EPSC 1. TUNU, EAST KALIMANTAN |
|
| TOTAL E&P INDONESIE , March 2005 - January 2007 |
|
| Engineering, Procurement, Supply, Pre-fabrication, Construction, Installation, Testing and Pre-Commissioning of the GTS's and all Components, Equipment and Materials thereto and Assistance to Company during commissioning and start-Up of the Plant. |
|
| -
The PLANT comprises |
|
- Four (4) new GTS's (Ax, Kx, Lx, Ix) with their associated Cold Vents as Extensions of Existing GTS
- Eleven (11) Associated Adjacent Wellhead Platforms
- Four (4) Reception Remote Wellhead Platforms, * Four (4) ESDV Platforms
- Associated Flowlines, Walkways and Offsites for Four (4) GTS's
- Tie-Ins Works of the New GTS's to the Existing Adjacent trunklines including new ESDV & Tripod
- New Extension and Integration of Telecommunication and Control System to TUNU Field Telemetry and Control System at Central Processing Unit (CPU) and TUNU North Processing Unit (NPU) - NCR Building
- Well Conductors Pipes ( 110 m' depth) for all Adjacent and Reception Remote Wellhead Platforms
|
|
| |
|
| ENGINEERING, PROCUREMENT, FABRICATION, INSTALLATION SERVICES CO2 REMOVAL PLANT PROJECT, LAWE-LAWE, EAST KALIMANTAN |
|
| UNOCAL INDONESIA Company , July 2001 - January 2002 |
|
| -
Engineering, Procurement, Fabrication and Installation. |
|
- Soil Investigation and Detail Design, - Transportation and Installation of Heavy Lift, - Civil Works
- Piping and Insulation Works, - Electrical and Instrument Works, - Equipment Installation
|
|
| |
|
| INSTALLATION OF LP GAS TRUNKLINE FROM SATELLITE # 6 TO # 5 NILAM FACILITY DEBOTTLENECKING PROJECT, NILAM, EAST KALIMANTAN |
|
| VICO INDONESIA , April 2001 - August 2001 |
|
| -
Installation of: 2 lines Trunkline Ø 10" River Crossing and 4 nos Scrapper Launcher / Receiver |
|
| -
Installation of: Electrical, Instrument and Civil Foundation |
|
| |
|
| TO PERFORM PROCUREMENT OF MATERIAL AND CONSTRUCTION / PIPING INSTALLATION FOR SLUG CATCHER ( M - 205 ) PROJECT, GRESIK, EAST JAVA |
|
| KODECO ENERGY Company Ltd , 2000 |
|
| -
Supply of Pipes, Valves and Fittings, - Supply Manway and Structural Platform |
|
| -
Construction Works: Tie-ins to the Existing, Slug Catcher |
|
| |
|
| ENGINEERING, SUPPLY AND INSTALLATION OF BADAK BUILDING AREA FIRE AND GAS PROTECTION SYSTEM (PHASE II), EAST KALIMANTAN |
|
| VICO INDONESIA , 1999 |
|
| -
Engineering, - Supply, Fabrication and Installation of:FGPS Panel, |
|
| -
Supply and Installation of Detectors, Field Wiring and Accessories, |
|
| -
Existing Fire and Gas Protection System Removal |
|
| -
Inspection, Testing and Commissioning |
|
| |
|
| PTA POLYPRIMA PROJEC, ANYER, WEST JAVA |
|
| P.T. POLYPRIMA KARYA REKSA , 1997 |
|
| - Piping Works: Vol. 240,000 Dia-in. Stainless Steel, Carbon Steel, Titanium, Hastelloy, PVC and FRP |
|
| - Erection of Steel Structure, weight 5,500 ton |
|
| -
Equipment Installation, weight 5,800 ton, The heaviest 240 ton highest 68 m |
|
| -
Assembly and installation of: 650 ton Stainless Steel: * Batch Tank: 2 units, * Silos: 2 units |
|
| -
C.S. Fuel Storage Tank: 1 unit |
|
| |
|
| GRESIK COPPER SMELTER PROJECT, GRESIK, EAST JAVA |
|
| CHIYODA INTERNATRIONAL INDONESIA (Main Contractor) , 1997 - 1998 |
|
| -
Piping Works: (PVC/FRP, CS, SS304 and 316, CS, Low Temperature, Galvanized) |
|
- Fabrication and Installation of Piping works for Process,Total work volume: 235,000 Dia -in.
|
|
| |
|
| DOW POLYMERS INDONESIA PROJECT, MERAK, WEST JAVA |
|
| P.T. DOW POLYMERS INDONESIA , 1994 |
|
| -
Equipment Installation and Alignment, 180 units |
|
| -
Piping Fabrication and Installation of: * Carbon Steel 30,852 Dia -in., * Pipe Support 20 ton |
|
| -
Installation of Prefabricated Steel Structure, Total weight: 594 ton |
|
| |
|
| 94 PREMIX BLENDING PLANT PROJECT, KALIBARU, TANJUNG PRIOK, JAKARTA |
|
| P.T. HUMPUSS , 1993 - 1994 |
|
| - Engineering, Procurement, Fabrication, Erection |
|
| - Testing, Inspection and Coating of Storage Tank: |
|
- 6,000 m3 ( Ø 24.38 x 12.8) m : 3 units, * 2,330 m3 ( Ø 15.24 x 12.8) m : 2 units
|
|
| - Piping Work: 20,000 Dia-in. - Pumps Installation |
|
| |
|