| RELOCATE NILAM LP COMPRESSOR - MUTIARA PROJECT, EAST KALIMANTAN |
|
| VICO INDONESIA , April 2006 - December 2006 |
|
| - Material supply and Compressor building |
|
| -
Equipment relocation, Pre-commissioning and Compressor package installation |
|
| -
Coolers and Vessel installations |
|
| |
|
| CONSTRUCTION OF BADAK VLP GAS COMPRESSION PROJECT, PHASE II BADAK, EAST KALIMANTAN |
|
| VICO INDONESIA , March 2004 - October 2004 |
|
| Installation of 1 x 30 MMSCFD Very Low Pressure (VLP) Gas Compression facilities at Badak Central Plant, included Suction Scrubber, Gas Cooler, Gas Filter, VLP Gas Production Separator and Gas Exchanger |
|
| -
Civil Works: |
|
- Compressor Building, Pipe Rack, Drainage System and Equipment Foundation
|
|
| -
Piping Works: 15,000 Dia-in. |
|
| -
Electrical & Instrumentation Works: |
|
- Fuel Instrument Gas System, Distribution System, Transformer and etc.
|
|
| -
Equipment Installation Works: |
|
- VLP Compressor Package, VLP Compressor Suction Scrubbe, VLP Compressor Fuel Gas Filter, Corrosion Inhibitor Skid, Fuel Gas Exchanger, VLP Gas Separator, Gas Cooler and Water / Condensate Pumps.
|
|
| |
|
| CONSTRUCTION OF MUTIARA MP GAS COMPRESSION PROJECT MUTIARA, EAST KALIMANTAN |
|
| VICO INDONESIA , April 2002 - October 2002 |
|
| Installation of 1 x 55 MMSCFD Medium Pressure (MP) Gas Compression Facilities at Mutiara Central Plant included Suction Scrubber, Gas Cooler, Gas Filter, MP Gas Production Separator and Gas Genset. |
|
| -
Civil Works: |
|
- Compressor Building, Pipe Rack, Burn Pit, Road Work and Drainage system
|
|
| - Piping Works: |
|
- All process Gas and Oil Works.
|
|
| -
Electrical & Instrumentation Works: |
|
- Switchgear and MCC, Electrical, Control equipments and etc.
|
|
| -
Equipment Installation Works: |
|
- AG Compressor Package and AG Compressor Suction Scrubber.
- AG Compression Fuel Gas Filter, Crane Hoist and Corrosion Inhibitor Skid.
|
|
| |
|
| NILAM LP GAS COMPRESSION FACILITIES PROJECT, NILAM, EAST KALIMANTAN |
|
| VICO INDONESIA , 1994 |
|
| -
Installation of 2 units Gas Turbine Compressor cap.: 35 MMSCFD at Nilam Satellite #2 and #4 |
|
| -
Installation of 4 nos Launcher and Receiver |
|
| -
Instalation of 2 units Flare Stack |
|
| -
Instalation 4 nos Condensate Pump |
|
| -
Fabrication and Installation of Piping |
|
- Total work volume: 39.000 Dia - In and Tie-In: 165 points.
|
|
| -
Civil Works |
|
- Compressor Building, Pipe Rack and Burn Pit.
- Road Work and Drainage System.
|
|
| |
|
| ASAHIMAS ANNUAL SHUTDOWN PROJECT, ANYER, WEST JAVA |
|
| P.T. ASAHI MAS SUBENTRA CHEMICAL , 1992 |
|
| -
Fabrication and Installation Piping Works |
|
- Lining Work for Tower TW - 2401 and Heat Exchanger : HE.24157 and HE. 24018.
|
|
| |
|