MECHANICAL, ELECTRICAL AND INSTRUMENTATION WORK
 
   
 
.............................................................................................................................................................................................................................
 
 
Fuel Distribution
 
     
     
 
CONSTRUCTION OF FUEL SUPPLY SYSTEM, NEW PADANG AIRPORT PROJECT PADANG, WEST SUMATERA  
THE DIRECTORATEGENERAL OF AIR COMMUNICATION. (JGC Corporation, Japan) - Main Contractor November 2003 - November 2004  
- Piping Works:  
  • Installation of 6,280 Dia-in aboveground Piping and Installation of 2,400 Dia-in underground Piping
 
- Equipment Erection Works:  
  • Design, Fabrication and Installation of Drain Drum Ø 1,800 x 5,500 mm: 2 units
  • Installation of Fuel Storage Distribution System: Pumps and Loading Arm
 
- Design, Fabrication and Erection of Storage Tanks:  
  • 3 units Dome Roof Tank, capacity 550 kl each and 1 unit Cone Roof Tank, Capacity 650 kl
 
- Electrical Works, - Instrument Works  
   
CONSTRUCTION OF FUEL SUPPLY SYSTEM, SURABAYA AIRPORT PROJECT SURABAYA, EAST JAVA  
THE DIRECTORATE GENERAL OF AIR COMMUNICATION. (JGC Corporation, Japan) - Main Contractor July 2002 - November 2005  
- Piling for Equipment and Tank Foundation: 302 nos Pile Concrete Pile (450 x 450 mm - 40 m length.)  
- Concrete Foundation and Structure, - Road Work, Pavement and Gravelling  
- Steel Structure Works: Walkway, Stage and Ladder Platform, etc.  
- Equipment Installation:  
  • Vessel: 22.30 ton each Pump and Ventilation Blower: 2 set
 
- Storage Tank Works:  
  • Design, Supply, Fabrication, Erection, NDT, Inspection, Hydrostatic test, Painting, Calibration
 
- Fuel Tank (4 units):  
  • Inside Ø 17.41 m, Height 10.5 m, Roof type: DRT, Capacity: 2,000 m3
 
-  Fire Water Tank (1 unit):  
  • Inside Ø 9.640 m, Height 10.8 m, Roof type: CRT, Capacity: 500 m3
 
- Diesel Oil Tank (1 unit):  
  • Inside Ø 3.370 m, Height 2.800 m, Roof type: CRT, Capacity 18 m3
 
- Piping Works:  
  • Aboveground Piping: 30,774 Dia-Inch (SS, CS, Galv., PVC).
  • Radiographic Inspection: 6,098 film.
  • Underground Piping: 13,294 Dia-Inch.(CS, Galv.).
  • Pipe Support: 7.50 ton ( CS Structure Steel
 
- Electrical Works, - Instrument Works  
   
CONSTRUCTION OF FUEL SUPPLY SYSTEM, BALI INTERNATIONAL AIRPORT DEVELOPMENT PROJECT, PHASE II, BALI ISLAND, INDONESIA  
THE DIRECTORATEGENERAL OF AIR COMMUNICATION (JGC Corporation, Japan) - Main Contractor 1998 - 2000  
- Site Development.   Civil Works :  
  • Sewer and Drainage, Road work and Paving, Concrete Structure, Steel Structure.
 
- Piping Works:  
  • Fabrication and Installation of Fuel Oil Line.
  • Utility line: Ø 16", length 2,000 m and Utility line: Ø 12", length 500 m
 
- Electrical and Instrument Works  
- Installation of Generator 750 Kva DCS System:  
  • MCC, Switch Gear, Transformer, Lighting, Grounding System
 
- Equipment Installation  
  • Installation of Fuel Pump, Hydrant Valves, Filter Separator
 
- Storage Tanks:  
  • Design, Supply, Fabrication, Installation, Painting and Testing of 3 units Tanks, Capacity 4,500 m3.
  • Dome Roof Tanks. ( Ø 19.35 x 16.46 m height) and Dome Roof Tanks. ( Ø 19.35 x 16.46 m height)
 
   
CONSTRUCTION OF FUEL DISTRIBUTION SYSTEM HANG NADIM AIRPORT PROJECT PHASE II BATAM ISLAND - RIAU  
THE DIRECTORATEGENERAL OF AIR COMMUNICATION. (NIIGATA Engineering Co. Ltd, Japan) - Main Contractor 1993 - 1995  
- Storage Tank Works:  
  • Intermediate Depot: 4 Units @ 10,000 m3 and Dome Roof Tank Ø 29.04 x 16.74 m height
 
- P.O.L Area:  
  • 4 units @ 3,000 m3, Ø 19.35 x 12.78 m height D.R.T. - Fuel Oil Tank. - Water Tank and 1 Unit @200 m3.
  • 1 Unit @ 1,800 m3Ø 13.55 x 14.58 m height C.R.T. - , * Ø 6.14 x 7.325 m height C.R.T. - Diesel Oil Tank.
 
- Piping Works:  
  • Intermidiate Depot Plant: 21,000 Dia-inch and P.O.L Plant = 23,000 Dia-inch.
  • Pipeline from P.O.L to APRON : + 2 x Ø 14", length ± 2.000 m, + 1 x Ø 14", length ± 1.500 m
 
- Pipeline Works:  
  • Depot Area to POL Plant : Ø 12", 6,600 m.
  • Equipment installation: + Installation of Fuel Pump, Water Pump, Generator, Oil Fiter, + Cyclone Separator, Gasoline Tank, Air Compressor Drain Tank, Diesel and Gasoline Dispencer, Pig launcer and Receiver, Fire Fighting System: Total weight ± 450 ton
 
- Civil and Building Works:  
  • Tank and Equipment Foundation, Pavement Work, Open Ditch, Bund Wall, Buildings and Sheds Header Pit, Valve Pit, Vent Pit etc. Header Pit, Valve Pit, Vent Pit etc.
 
- Electrical Works:  
  • Installation of Electrical Equipment: MCC, Switchgear, Transformer etc.
  • Lighting System, Cathodic Protection, Cabling and Connection, and Telephone System
 
- Instrumentation Works:  
  • Installation of Fuel Storage Distribution System, Pumps, and Loading Arm, Installation of Instrument Equipment.
  • Instrument Hook Up and Control System